Tools, Assembly and Test Equipment
Data Center
Tools, assembly and test equipment brings together everything needed between pipe, hose and fitting when a liquid cooling circuit in a data centre is built or maintained: pipe deburring tools from 3 to 56 mm, ratchet hose cutters up to 63 mm, depth marking tools for connectors of 35 to 54 mm diameter, plus assembly pastes, silicone greases and cleaning agents for final installation. The branch currently holds 22 items from Fluidics equipment, OKS, Riegler and Henkel and covers the working steps that decide whether a joint stays tight long before coolant enters the system.
In water-glycol circuits the sequence matters: cut to length, deburr, mark the insertion depth, tighten to a defined torque, then pressure test and leak check. Burrs and swarf left from cutting otherwise travel into pumps, heat exchangers and cold plates. Four of the seven subcategories currently describe only their function in the circuit: pressing and crimping tools, flushing equipment, pressure testing and leak detection fluids are still being built up and show the gap openly.
Categories



From cutting to handover - which step calls for which tool
| Working step | Tool or consumable | Risk if skipped | Subcategory |
|---|---|---|---|
| Cutting to length | Ratchet hose cutters 0 - 42 and 0 - 63 mm | Angled cut, the sealing face does not bear all round | Pipe and hose processing |
| Deburring | Pipe deburring tools 3 - 42, 8 - 35 and 10 - 56 mm | Burrs score O-rings, swarf stays in the circuit | Pipe and hose processing |
| Marking insertion depth | Depth marking and deburring tool, 35 - 54 mm diameter | Connector seats too shallow and releases under pressure | Pipe and hose processing |
| Tightening | Torque wrench, assembly paste | Over-tightening cracks the cutting ring, too little torque leaks | Torque and assembly tools |
| Lubricating and locking | OKS 1149 and OKS 1111 silicone grease, threadlocker | Valve spindles seize, screwed joints work loose | Assembly pastes, valve grease, threadlockers |
| Flushing | Filtered flushing loop, pipe cleaner | Particles from cutting reach the cold plate | Flushing and cleaning equipment (in preparation) |
| Testing | Pressure test, leak detection spray | Leakage only becomes visible in service, above live electronics | Pressure testing and leak detection (in preparation) |
- First installation of chilled water and water-glycol circuits in rack and in-row cooling
- Assembly of hoses and pipes for cold plates and manifolds
- Maintenance on fittings, couplings and valves during operation
- Handover with documented tightening torques before the first fill
- Repair work after rebuilding or extending a cooling row
- Fault finding on drip leaks in the rack and on supply lines